Lake Major Dam Replacement
Federal contribution
$2.3M
$2,258,858
Federal share50%
of $4.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 16, 2016
201720182019
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Halifax Regional Water Commission
- Construction start
- Jun 1, 2018(actual)
- Construction end
- Oct 1, 2019(actual)
Against the original forecast
- Construction start3 months lateforecast Mar 1, 2018
- Construction end6 months earlyforecast Mar 31, 2020
Also in Halifax
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47226 in the federal list. How to read these figures.