Back to projects

Sullivan's pond storm sewer renewal - phase 1

Halifax, Nova Scotia

completeWastewaterCWWF
Federal contribution
$4.2M
$4,214,595
Federal share50%

of $8.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 16, 2016
20172018
Built
Program
Clean Water and Wastewater Fund
Construction start
May 19, 2017(actual)
Construction end
Feb 22, 2018(actual)

Against the original forecast

  • Construction start3 weeks lateforecast May 1, 2017
  • Construction end8 months earlyforecast Oct 30, 2018