J. D. Kline Filter Media and Underdrain Replacement
Federal contribution
$2.1M
$2,100,080
Federal share50%
of $4.2M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 16, 2016
2017201820192020
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Halifax Regional Water Commission
- Construction start
- Feb 5, 2018(actual)
- Construction end
- Mar 2, 2020(actual)
Against the original forecast
- Construction start5 weeks lateforecast Jan 1, 2018
- Construction end4 weeks earlyforecast Mar 31, 2020
Also in Halifax