J. D. Kline Filter Media and Underdrain Replacement

Halifax, Nova Scotia

completeDrinking WaterCWWF
Federal contribution
$2.1M
$2,100,080
Federal share50%

of $4.2M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 16, 2016
2017201820192020
Built
Program
Clean Water and Wastewater Fund
Construction start
Feb 5, 2018(actual)
Construction end
Mar 2, 2020(actual)

Against the original forecast

  • Construction start5 weeks lateforecast Jan 1, 2018
  • Construction end4 weeks earlyforecast Mar 31, 2020

Also in Halifax

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47228 in the federal list. How to read these figures.