Maple street / old deepdale road water and sewer extension
Federal contribution
$297,424
Federal share50%
of $594.8K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 16, 2016
2017
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Municipality of the County of Inverness
- Construction start
- Nov 1, 2016(actual)
- Construction end
- Nov 1, 2017(actual)
Against the original forecast
- Construction start6 months earlyforecast May 1, 2017
- Construction end5 months earlyforecast Mar 31, 2018
Also in Hantsport
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47239 in the federal list. How to read these figures.