Back to projects

French cove water extension

Richmond, Nova Scotia

completeDrinking WaterCWWF
Federal contribution
$188,069
Federal share50%

of $378.6K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 16, 2016
201720182019
Built
Program
Clean Water and Wastewater Fund
Construction start
Dec 1, 2017(actual)
Construction end
Dec 4, 2018(actual)

Against the original forecast

  • Construction start5 weeks lateforecast Oct 30, 2017
  • Construction end4 months earlyforecast Mar 31, 2019

Also in Richmond

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47244 in the federal list. How to read these figures.