Sherbrooke water distribution system - waterline replacement
Federal contribution
$862,920
Federal share50%
of $1.7M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 16, 2016
20172018
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Municipality of the District of St. Mary's
- Construction start
- Oct 30, 2017(actual)
- Construction end
- May 17, 2018(actual)
Against the original forecast
- Construction start4 weeks lateforecast Oct 2, 2017
- Construction end10 months earlyforecast Mar 31, 2019