Toronto Rocket / T1 Rail Yard Accommodation
Federal contribution
$24.4M
$24,353,500
Federal share50%
of $48.7M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedAug 23, 2016
ApprovedJul 10, 2017
2017201820192020
Built
Approved 11 months after the announcement.
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- City of Toronto
- Construction start
- Apr 1, 2016(actual)
- Construction end
- Mar 24, 2020(actual)
Against the original forecast
- Construction start2 months earlyforecast Jun 1, 2016
- Construction end16 months earlyforecast Jul 31, 2021
Also in Toronto