Subway Facility Renewal Program

Toronto, Ontario

completePublic TransitPTIF
Federal contribution
$2.7M
$2,666,824
Federal share44%

of $6.1M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedAug 23, 2016
ApprovedJul 10, 2017
2017201820192020
Built

Approved 11 months after the announcement.

Program
Public Transit Infrastructure Fund
Ultimate recipient
City of Toronto
Construction start
Aug 1, 2016(actual)
Construction end
Mar 31, 2020(actual)

Against the original forecast

  • Construction start4 weeks lateforecast Jul 1, 2016
  • Construction end3 months lateforecast Dec 31, 2019

Also in Toronto

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47270 in the federal list. How to read these figures.