Subway Track Rehabilitation Program
Federal contribution
$17.7M
$17,702,500
Federal share50%
of $35.4M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedAug 23, 2016
ApprovedMar 27, 2018
201720182019202020212022
Built
Approved 19 months after the announcement.
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- City of Toronto
- Construction start
- Apr 1, 2016(actual)
- Construction end
- Dec 31, 2021(actual)
Against the original forecast
- Construction end12 months earlyforecast Dec 31, 2022
Also in Toronto
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47286 in the federal list. How to read these figures.