Back to projects

Subway Turnout Rehabilitation Program

Toronto, Ontario

completePublic TransitPTIF
Federal contribution
$12.8M
$12,756,235
Federal share50%

of $25.6M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedAug 23, 2016
ApprovedMar 27, 2018
20172018201920202021
Built

Approved 19 months after the announcement.

Program
Public Transit Infrastructure Fund
Ultimate recipient
City of Toronto
Construction start
Apr 1, 2016(actual)
Construction end
Jul 31, 2021(actual)

Also in Toronto

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47287 in the federal list. How to read these figures.