Subway Workcars

Toronto, Ontario

completePublic TransitPTIF
Federal contribution
$12.7M
$12,658,192
Federal share50%

of $25.5M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedAug 23, 2016
ApprovedMar 27, 2018
20172018201920202021
Built

Approved 19 months after the announcement.

Program
Public Transit Infrastructure Fund
Ultimate recipient
City of Toronto
Construction start
Apr 1, 2016(actual)
Construction end
Jul 26, 2021(actual)

Against the original forecast

  • Construction end12 months earlyforecast Jul 31, 2022