Surface Special Trackwork Replacement Program

Toronto, Ontario

completePublic TransitPTIF
Federal contribution
$6.8M
$6,784,500
Federal share50%

of $13.6M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedAug 23, 2016
ApprovedJul 10, 2017
20172018
Built

Approved 11 months after the announcement.

Program
Public Transit Infrastructure Fund
Ultimate recipient
City of Toronto
Construction start
Jan 1, 2017(actual)
Construction end
Dec 31, 2017(actual)

Against the original forecast

  • Construction end3 months earlyforecast Mar 31, 2018