Schedule

Announced and approvedAug 18, 2016
201720182019
Built
Program
Clean Water and Wastewater Fund
Ultimate recipient
Town of Sackville
Construction start
May 29, 2017(actual)
Construction end
Nov 8, 2019(actual)

Against the original forecast

  • Construction start4 weeks lateforecast May 1, 2017
  • Construction end6 weeks lateforecast Sep 30, 2019