Lorne Street - Water, Sanitary, and Storm Infrastructure Upgrades with Storm Water Mitigation
Federal contribution
$2.7M
$2,680,523
Federal share50%
of $5.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 18, 2016
201720182019
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Town of Sackville
- Construction start
- May 29, 2017(actual)
- Construction end
- Nov 8, 2019(actual)
Against the original forecast
- Construction start4 weeks lateforecast May 1, 2017
- Construction end6 weeks lateforecast Sep 30, 2019