Bus Hoists
Federal contribution
$1.7M
$1,735,014
Federal share45%
of $3.8M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedAug 23, 2016
ApprovedJul 10, 2017
2017
Built
Approved 11 months after the announcement.
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- City of Toronto
- Construction start
- Oct 1, 2016(actual)
- Construction end
- Jun 30, 2017(actual)
Against the original forecast
- Construction start3 months lateforecast Jul 1, 2016
- Construction end21 months earlyforecast Mar 31, 2019
Also in Toronto
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47346 in the federal list. How to read these figures.