Platform Modifications to Accommodate Articulated Buses

Toronto, Ontario

completePublic TransitPTIF
Federal contribution
$1.9M
$1,875,000
Federal share50%

of $3.8M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedAug 23, 2016
ApprovedMar 27, 2018
201720182019
Built

Approved 19 months after the announcement.

Program
Public Transit Infrastructure Fund
Ultimate recipient
City of Toronto
Construction start
Mar 1, 2017(actual)
Construction end
Jul 1, 2019(actual)

Against the original forecast

  • Construction start6 months lateforecast Sep 1, 2016
  • Construction end6 months earlyforecast Dec 31, 2019

Also in Toronto

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47349 in the federal list. How to read these figures.