Storage Tanks - Oil Interceptors
Federal contribution
$608,865
Federal share49%
of $1.2M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedAug 23, 2016
ApprovedJul 10, 2017
20172018
Built
Approved 11 months after the announcement.
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- City of Toronto
- Construction start
- Jun 1, 2017(actual)
- Construction end
- Mar 31, 2018(actual)
Against the original forecast
- Construction start6 months lateforecast Dec 1, 2016
- Construction end12 months earlyforecast Mar 31, 2019
Also in Toronto