Back to projects

Storage Tanks - Oil Interceptors

Toronto, Ontario

completePublic TransitPTIF
Federal contribution
$608,865
Federal share49%

of $1.2M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedAug 23, 2016
ApprovedJul 10, 2017
20172018
Built

Approved 11 months after the announcement.

Program
Public Transit Infrastructure Fund
Ultimate recipient
City of Toronto
Construction start
Jun 1, 2017(actual)
Construction end
Mar 31, 2018(actual)

Against the original forecast

  • Construction start6 months lateforecast Dec 1, 2016
  • Construction end12 months earlyforecast Mar 31, 2019

Also in Toronto

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47369 in the federal list. How to read these figures.