Relief Line Planning and Design
Federal contribution
$22.0M
$22,045,823
Federal share40%
of $55.5M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedAug 23, 2016
ApprovedMar 27, 2018
201720182019
Built
Approved 19 months after the announcement.
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- City of Toronto
- Construction start
- Dec 1, 2017(actual)
- Construction end
- Oct 31, 2019(actual)
Against the original forecast
- Construction start20 months lateforecast Apr 1, 2016
- Construction end2 months earlyforecast Dec 31, 2019
Also in Toronto
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47378 in the federal list. How to read these figures.