Waterfront Transit Design

Toronto, Ontario

completePublic TransitPTIF
Federal contribution
$491,637
Federal share14%

of $3.6M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedAug 23, 2016
ApprovedMar 27, 2018
2017201820192020
Built

Approved 19 months after the announcement.

Program
Public Transit Infrastructure Fund
Ultimate recipient
City of Toronto
Construction start
Nov 1, 2017(actual)
Construction end
Mar 31, 2020(actual)

Against the original forecast

  • Construction start19 months lateforecast Apr 1, 2016
  • Construction end3 months lateforecast Dec 31, 2019