Back to projects

Eglinton Connects Streetscape Improvements and Cycle Tracks

Toronto, Ontario

completeActive TransportationPTIF
Federal contribution
$896,449
Federal share36%

of $2.5M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedAug 23, 2016
ApprovedMar 27, 2018
2017201820192020
Built

Approved 19 months after the announcement.

Program
Public Transit Infrastructure Fund
Ultimate recipient
City of Toronto
Construction start
Jun 1, 2017(actual)
Construction end
Mar 31, 2020(actual)

Against the original forecast

  • Construction start3 months earlyforecast Sep 1, 2017
  • Construction end3 months lateforecast Dec 31, 2019

Also in Toronto

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47380 in the federal list. How to read these figures.