New mid-block crossings to transit stops
Federal contribution
$451,709
Federal share15%
of $3.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 23, 2016
2017201820192020
Built
Approved 4 weeks before the announcement.
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- City of Toronto
- Construction start
- May 1, 2017(actual)
- Construction end
- Aug 31, 2020(actual)
Against the original forecast
- Construction start4 weeks lateforecast Apr 1, 2017
- Construction end4 months earlyforecast Dec 31, 2020