Reductions of curb radii at key intersections

Toronto, Ontario

completePublic TransitPTIF
Federal contribution
$1.1M
$1,136,961
Federal share50%

of $2.3M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedAug 23, 2016
ApprovedMar 27, 2018
2017201820192020
Built

Approved 19 months after the announcement.

Program
Public Transit Infrastructure Fund
Ultimate recipient
City of Toronto
Construction start
Jul 1, 2016(actual)
Construction end
Aug 31, 2020(actual)

Against the original forecast

  • Construction end11 months earlyforecast Jul 31, 2021

Also in Toronto

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47396 in the federal list. How to read these figures.