Missing Sidewalk Links - 2017

Toronto, Ontario

completePublic TransitPTIF
Federal contribution
$657,797
Federal share50%

of $1.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 23, 2016
2017201820192020
Built

Approved 4 weeks before the announcement.

Program
Public Transit Infrastructure Fund
Ultimate recipient
City of Toronto
Construction start
Apr 1, 2017(actual)
Construction end
Aug 24, 2020(actual)

Against the original forecast

  • Construction end11 months earlyforecast Jul 31, 2021