Missing sidewalk links - 2018 Road Safety Plan
Federal contribution
$184,306
Federal share37%
of $500.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 23, 2016
2017201820192020
Built
Approved 4 weeks before the announcement.
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- City of Toronto
- Construction start
- Jan 1, 2018(actual)
- Construction end
- Aug 24, 2020(actual)
Against the original forecast
- Construction end4 months earlyforecast Dec 31, 2020