Pavement Marking Improvements
Federal contribution
$200,000
Federal share50%
of $400.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 23, 2016
20172018
Built
Approved 4 weeks before the announcement.
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- City of Toronto
- Construction start
- May 21, 2017(actual)
- Construction end
- Jun 30, 2018(actual)
Against the original forecast
- Construction start3 weeks lateforecast May 1, 2017
- Construction end6 months earlyforecast Dec 31, 2018
Also in Toronto
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47405 in the federal list. How to read these figures.