Pavement Marking Improvements

Toronto, Ontario

completePublic TransitPTIF
Federal contribution
$200,000
Federal share50%

of $400.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 23, 2016
20172018
Built

Approved 4 weeks before the announcement.

Program
Public Transit Infrastructure Fund
Ultimate recipient
City of Toronto
Construction start
May 21, 2017(actual)
Construction end
Jun 30, 2018(actual)

Against the original forecast

  • Construction start3 weeks lateforecast May 1, 2017
  • Construction end6 months earlyforecast Dec 31, 2018

Also in Toronto

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47405 in the federal list. How to read these figures.