LED Blank-Out Signs for turn restrictions
Federal contribution
$186,680
Federal share25%
of $760.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 23, 2016
2017201820192020
Built
Approved 4 weeks before the announcement.
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- City of Toronto
- Construction start
- May 21, 2017(actual)
- Construction end
- Jun 30, 2020(actual)
Against the original forecast
- Construction start3 weeks lateforecast May 1, 2017
- Construction end13 months earlyforecast Jul 31, 2021