Ross River Pedestrian Bridge Upgrades

Ross River, Yukon

completePublic TransitSCF
Federal contribution
$3.2M
$3,163,061
Federal share73%

of $4.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJan 10, 2017
20172018
Built

Approved 4 months before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Construction start
Aug 25, 2017(actual)
Construction end
Jun 30, 2018(actual)

Against the original forecast

  • Construction start3 months earlyforecast Nov 15, 2017
  • Construction end9 months earlyforecast Mar 31, 2019

Also in Ross River

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47420 in the federal list. How to read these figures.