Ross River Sewage Lagoon

Ross River, Yukon

completeWastewaterCWWF
Federal contribution
$1.7M
$1,657,662
Federal share67%

of $2.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 22, 2016
201720182019
Built
Program
Clean Water and Wastewater Fund
Ultimate recipient
Government of Yukon
Construction start
Aug 11, 2017(actual)
Construction end
Aug 29, 2019(actual)

Against the original forecast

  • Construction start13 months lateforecast Jul 1, 2016
  • Construction end19 months earlyforecast Mar 31, 2021