Increase Specialized Transit Fleet
Federal contribution
$39,943
Federal share50%
of $80.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 23, 2016
20172018
Built
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- City of Greater Sudbury
- Construction start
- Apr 1, 2017(actual)
- Construction end
- Apr 30, 2018(actual)
Against the original forecast
- Construction end4 weeks lateforecast Mar 31, 2018