Conventional Transit Bus Replacement 2016
Federal contribution
$1.3M
$1,309,771
Federal share50%
of $2.6M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 23, 2016
2017
Built
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- City of Barrie
- Construction start
- Mar 1, 2017(actual)
- Construction end
- Jul 1, 2017(actual)
Against the original forecast
- Construction start4 months lateforecast Nov 1, 2016
- Construction end4 weeks lateforecast May 31, 2017
Also in Barrie
- Allandale Mobility Hub & Downtown Connection Hub - Construction$9.9M
- Conventional Fleet Replacement$9.4M
- HVAC upgrades for schools and portables; Purchase of new portables; Window replacement$8.0M
- Sanitary Servicing to Reduce Phosphorus to Lake Simcoe- Royal Oak, Bay, Cottage Lane$5.3M
- Construction of a New Fire and Emergency Services Station and Headquarters$4.3M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47486 in the federal list. How to read these figures.