17th Avenue Southeast – Bus Rapid Transit - Phase 2

Calgary, Alberta

completePublic TransitPTIF
Federal contribution
$42.5M
$42,500,000
Federal share50%

of $85.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 1, 2016
2017201920212023
Built
Program
Public Transit Infrastructure Fund
Ultimate recipient
City of Calgary
Construction start
Oct 1, 2016(actual)
Construction end
Nov 30, 2023(actual)

Against the original forecast

  • Construction start6 months lateforecast Apr 1, 2016
  • Construction end3 months lateforecast Aug 31, 2023

Also in Calgary

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47499 in the federal list. How to read these figures.