Light Rail Vehicles
Federal contribution
$12.5M
$12,500,000
Federal share50%
of $25.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 1, 2016
2017201920212023
Built
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- City of Calgary
- Construction start
- Apr 10, 2017(actual)
- Construction end
- Nov 15, 2023(actual)
Against the original forecast
- Construction start12 months lateforecast Apr 1, 2016
- Construction end10 months lateforecast Dec 31, 2022
Also in Calgary
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47502 in the federal list. How to read these figures.