Regional Water Phase 3 - Stage 2 - St. Isidore to Nampa
Federal contribution
$2.6M
$2,571,174
Federal share36%
of $7.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 1, 2016
20172018
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Municipal District of Northern Sunrise
- Construction start
- Feb 13, 2017(actual)
- Construction end
- Nov 28, 2018(actual)
Against the original forecast
- Construction start3 months lateforecast Nov 1, 2016
- Construction end4 months earlyforecast Mar 31, 2019
Also in Nampa
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47572 in the federal list. How to read these figures.