Back to projects

Regional Water Phase 3 - Stage 2 - St. Isidore to Nampa

Nampa, Alberta

completeDrinking WaterCWWF
Federal contribution
$2.6M
$2,571,174
Federal share36%

of $7.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 1, 2016
20172018
Built
Program
Clean Water and Wastewater Fund
Construction start
Feb 13, 2017(actual)
Construction end
Nov 28, 2018(actual)

Against the original forecast

  • Construction start3 months lateforecast Nov 1, 2016
  • Construction end4 months earlyforecast Mar 31, 2019

Also in Nampa