County of Forty Mile/Foremost Manyberries Regional Pipeline

Foremost, Alberta

completeDrinking WaterCWWF
Federal contribution
$3.0M
$3,041,362
Federal share49%

of $6.2M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 1, 2016
20172018201920202021
Built
Program
Clean Water and Wastewater Fund
Ultimate recipient
County of Forty Mile No. 8
Construction start
Jul 19, 2017(actual)
Construction end
Dec 31, 2020(actual)

Against the original forecast

  • Construction end12 months lateforecast Dec 31, 2019

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47588 in the federal list. How to read these figures.