Lamont County Regional Water Supply - St Michael

St. Michael, Alberta

completeDrinking WaterCWWF
Federal contribution
$2.3M
$2,271,886
Federal share34%

of $6.8M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 1, 2016
2017201820192020
Built
Program
Clean Water and Wastewater Fund
Construction start
Sep 16, 2017(actual)
Construction end
Mar 4, 2020(actual)

Against the original forecast

  • Construction start6 months lateforecast Apr 1, 2017
  • Construction end11 months lateforecast Mar 31, 2019

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47590 in the federal list. How to read these figures.