Public Transit Upgrades

Yellowknife, Northwest Territories

completePublic TransitPTIF
Federal contribution
$253,850
Federal share59%

of $426.7K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 6, 2016
2017201820192020
Built
Program
Public Transit Infrastructure Fund
Ultimate recipient
City of Yellowknife
Construction start
Jun 1, 2017(actual)
Construction end
Mar 31, 2020(actual)

Against the original forecast

  • Construction end4 months lateforecast Dec 1, 2019