Transit Technology and Software Improvements
Federal contribution
$582,891
Federal share50%
of $1.2M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 16, 2016
20172018
Built
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- City of Regina
- Construction start
- Sep 15, 2016(actual)
- Construction end
- Sep 30, 2018(actual)
Against the original forecast
- Construction start4 months earlyforecast Jan 1, 2017
- Construction end4 weeks lateforecast Aug 31, 2018
Also in Regina
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47655 in the federal list. How to read these figures.