Intelligent Transportation and Data Requirements
Federal contribution
$1.0M
$1,000,000
Federal share50%
of $2.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 16, 2016
2017201820192020
Built
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- City of Saskatoon
- Construction start
- Nov 30, 2016(actual)
- Construction end
- Apr 9, 2020(actual)
Against the original forecast
- Construction start3 months lateforecast Sep 1, 2016
- Construction end6 months earlyforecast Sep 30, 2020
Also in Saskatoon
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47669 in the federal list. How to read these figures.