Kimberley Drinking Water Loss Management

Kimberley, British Columbia

completeDrinking WaterCWWF
Federal contribution
$467,966
Federal share50%

of $935.9K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 30, 2016
201720182019
Built
Program
Clean Water and Wastewater Fund
Ultimate recipient
City of Kimberley
Construction start
Sep 25, 2017(actual)
Construction end
Mar 31, 2019(actual)

Against the original forecast

  • Construction start4 months lateforecast May 30, 2017
  • Construction end3 months lateforecast Dec 31, 2018