Kimberley Drinking Water Loss Management
Federal contribution
$467,966
Federal share50%
of $935.9K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 30, 2016
201720182019
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- City of Kimberley
- Construction start
- Sep 25, 2017(actual)
- Construction end
- Mar 31, 2019(actual)
Against the original forecast
- Construction start4 months lateforecast May 30, 2017
- Construction end3 months lateforecast Dec 31, 2018
Also in Kimberley
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47686 in the federal list. How to read these figures.