Back to projects

Warfield Pressure Reducing Valve Stations Rehabilitation

Warfield, British Columbia

completeDrinking WaterCWWF
Federal contribution
$111,000
Federal share50%

of $222.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 30, 2016
20172018
Built
Program
Clean Water and Wastewater Fund
Ultimate recipient
Village of Warfield
Construction start
May 16, 2017(actual)
Construction end
May 31, 2018(actual)

Against the original forecast

  • Construction start10 months earlyforecast Mar 5, 2018
  • Construction end4 weeks lateforecast Apr 30, 2018

Also in Warfield