Recreation Centre Upgrades

Fort Simpson, Northwest Territories

completeRecreationSCF
Federal contribution
$1.1M
$1,149,500
Federal share75%

of $1.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJan 27, 2017
20172019202120232025
Built

Approved 6 weeks before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
Village of Fort Simpson
Construction start
Apr 1, 2020(actual)
Construction end
Dec 3, 2024(actual)

Against the original forecast

  • Construction end11 months lateforecast Dec 31, 2023

Also in Fort Simpson

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47754 in the federal list. How to read these figures.