Fort Simpson Community Chipseal

Fort Simpson, Northwest Territories

completeHighways and RoadsRNIS
Federal contribution
$1.7M
$1,672,995
Federal share69%

of $2.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 13, 2019
2020
Built

Approved 4 weeks before the announcement.

Program
Rural & Northern Infrastructure Stream
Ultimate recipient
Village of Fort Simpson
Construction start
Jul 1, 2020(actual)
Construction end
Oct 1, 2020(actual)

Against the original forecast

  • Construction start7 weeks lateforecast May 15, 2020
  • Construction end4 weeks earlyforecast Oct 31, 2020

Also in Fort Simpson

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 54108 in the federal list. How to read these figures.