Arena Upgrade and Community Hall Replacement

Fort McPherson, Northwest Territories

completeRecreationSCF
Federal contribution
$1.0M
$1,038,000
Federal share19%

of $5.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJan 27, 2017
2017201920212023
Built

Approved 6 weeks before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
Hamlet of Fort McPherson
Construction start
May 1, 2020(actual)
Construction end
Oct 31, 2022(actual)

Against the original forecast

  • Construction start4 weeks earlyforecast Jun 1, 2020
  • Construction end2 months lateforecast Sep 1, 2022

Also in Fort McPherson

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47762 in the federal list. How to read these figures.