Piped W&S Priority Upgrades
Fort McPherson, Northwest Territories
Federal contribution
$750,000
Federal share75%
of $1.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 6, 2016
20172018201920202021
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Hamlet of Fort McPherson
- Construction start
- Sep 14, 2018(actual)
- Construction end
- Dec 31, 2020(actual)
Against the original forecast
- Construction start4 months lateforecast May 1, 2018
- Construction end4 weeks lateforecast Nov 30, 2020
Also in Fort McPherson
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47629 in the federal list. How to read these figures.