Transit Facility Expansion to meet ridership demand
Federal contribution
$761,973
Federal share33%
of $2.3M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedFeb 10, 2017
ApprovedJul 10, 2017
20182019
Built
Approved 5 months after the announcement.
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- City of Belleville
- Construction start
- May 6, 2018(actual)
- Construction end
- May 31, 2019(actual)
Against the original forecast
- Construction start7 months lateforecast Oct 4, 2017
- Construction end7 months earlyforecast Dec 31, 2019
Also in Belleville