Expansion and Replacement of Transit Amenities

Brampton, Ontario

completePublic TransitPTIF
Federal contribution
$999,757
Federal share50%

of $2.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 10, 2017
201720182019
Built

Approved 2 months before the announcement.

Program
Public Transit Infrastructure Fund
Construction start
Apr 1, 2017(actual)
Construction end
Oct 4, 2019(actual)

Against the original forecast

  • Construction start3 months lateforecast Jan 1, 2017
  • Construction end6 months earlyforecast Mar 31, 2020