Replacement and new bus shelters
Federal contribution
$7,543
Federal share38%
of $20.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 10, 2017
2017201820192020
Built
Approved 2 months before the announcement.
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- City of Brockville
- Construction start
- Mar 4, 2019(actual)
- Construction end
- Dec 31, 2019(actual)
Against the original forecast
- Construction start8 weeks earlyforecast May 1, 2019
- Construction end5 months lateforecast Aug 1, 2019
Also in Brockville
- Brockville Water Pollution Control Centre Upgrade$22.3M
- Construction of the Maritime Discovery Centre of the 1000 Islands (MDC)$5.7M
- HVAC, Bottle Water Filling Station, Portable, Retrofits, Wifi, Windows$5.2M
- Automatic Door Opener; Video Camera Childcare Project Group; Washroom Project Group; Site Project Group; HVAC Ventilation Upgrades$2.1M
- To replace aging HVAC Equipment and Controls.$2.0M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47777 in the federal list. How to read these figures.