Green Line LRT - Utility Relocations - SE Corridor
Federal contribution
$25.0M
$25,000,000
Federal share50%
of $50.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedDec 3, 2016
201720182019202020212022
Built
Approved 4 weeks before the announcement.
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- City of Calgary
- Construction start
- Apr 1, 2016(actual)
- Construction end
- Jun 30, 2022(actual)
Also in Calgary
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47814 in the federal list. How to read these figures.