Green Line LRT - Transit Bus Improvements
Federal contribution
$2.5M
$2,500,000
Federal share50%
of $5.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedDec 3, 2016
201720182019202020212022
Built
Approved 4 weeks before the announcement.
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- City of Calgary
- Construction start
- Oct 1, 2016(actual)
- Construction end
- Jun 25, 2022(actual)
Against the original forecast
- Construction start6 months lateforecast Apr 1, 2016
- Construction end3 months lateforecast Mar 31, 2022