New Whitecourt Transit Bus
Federal contribution
$74,000
Federal share19%
of $400.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedDec 3, 2016
20172018
Built
Approved 4 weeks before the announcement.
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- Town of Whitecourt
- Construction start
- May 1, 2017(actual)
- Construction end
- Jun 30, 2018(actual)
Against the original forecast
- Construction start2 months lateforecast Mar 1, 2017
- Construction end6 months earlyforecast Dec 31, 2018
Also in Whitecourt