New Whitecourt Transit Bus

Whitecourt, Alberta

completePublic TransitPTIF
Federal contribution
$74,000
Federal share19%

of $400.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedDec 3, 2016
20172018
Built

Approved 4 weeks before the announcement.

Program
Public Transit Infrastructure Fund
Ultimate recipient
Town of Whitecourt
Construction start
May 1, 2017(actual)
Construction end
Jun 30, 2018(actual)

Against the original forecast

  • Construction start2 months lateforecast Mar 1, 2017
  • Construction end6 months earlyforecast Dec 31, 2018

Also in Whitecourt

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47831 in the federal list. How to read these figures.