Purchase three 60' buses and nine 40' buses to replace existing vehicles for conventional service
Federal contribution
$3.6M
$3,578,855
Federal share46%
of $7.7M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 31, 2017
20172018
Built
Approved 3 months before the announcement.
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- Corporation of the City of St. Catharines
- Construction start
- Mar 31, 2017(actual)
- Construction end
- Apr 17, 2018(actual)
Against the original forecast
- Construction end2 weeks lateforecast Mar 31, 2018
Also in St. Catharines
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47885 in the federal list. How to read these figures.